ESE Current Projects – 2024:

Currently, we are executing contracts for private accommodations and other government projects.

  • Electrical & Infrastructure work – AMAALA (Marina Triple Bay).

Client: Red Sea

Project Budget: 20 Millions SAR

Duration: 12 Months

 

 

  • HVAC Installation work – Dr. Soliman Fakeeh Hospital

Client: Dr. Soliman Fakeeh Hospital
Project Budget: 10 Millions SAR
Duration: 1 Year

  • HVAC Installation work – Neom Project

Client: NEOM
Project Budget: 3,2 Millions SAR
Duration: 6 Months

  • Electricity & Lightning Project – King’s College Hospital Jeddah

Client: King’s College Hospital Jeddah
Project Budget: 3.9 Millions SAR
Duration: 6 Months

   

  • Sanitary System Project – King’s College Hospital Jeddah

Client: King’s College Hospital

Project Budget: 4.2 Millions SAR

Duration: 6 Months