ESE Executed Projects: 

We have successfully executed various buildings on design and build basis. In addition, ESE Currently is executing private accommodations and other governmental contracts.

 

  1. Renovation & Modification of AL-ISKAN Primary Health Care Clinic at King Abdul-Aziz Medical City.

 

Client: National Guard – Health affairs

Project Budget: 0.5 Million SR

Project Duration: 6 months

                       

 

  1. Replacement of ATS for (EPGU) Emergency Power Generator Unit at the Powerhouse in National Guard Health Affairs.

Client: National Guard – Health affairs

Project Budget: 0.4 Million SR

Project Duration: 3 months

 

                                   

 

  1. Supply & installation of HVAC system for data center.

 

Client: Ministry of interior

Project Budget: 2.5 Million SR

Project Duration: 9 months

  

 

 

  1. Supply & installation of complete BMS for Admin Building.

 

Client: M. Waleed A. Al-Ghazzawe EST. – National Guard Health affairs

Project Budget: 0.75 Million SR

Project Duration: 5 months

 

   

 

 

  1. Supply & installation of fuel (Diesel) piping system.

 

Client: Al-Boaiz Comp. – National Guard – Health affairs

Project Budget: 0.90 Million SR

Project Duration: 6 months

 

  

 

  1. Supply & installation of Emergency Power Generator Units.

 

Client: Al-Boaiz Comp. – National Guard – Health affairs

Project Budget: 3.75 Million SR

Project Duration: 6 months

 

 

  1. Supply & installation of HVAC system.

 

Client: Qlae Al-Ensha Comp. – National Guard – Health affairs

Project Budget: 0.95 Million SR

Project Duration: 6 months

 

   

 

 

 

  1. Supply & installation of firefighting system for HR Buildings.

 

Client: Guarantee Business EST. – National Guard Health affairs

Project Budget: 1.7 Million SR

Project Duration: 9 months

                           

 

  1. Supply & installation of firefighting system for PHC in Taif.

Client: Guarantee Business EST. – National Guard Health affairs

Project Budget: 0.3 Million SR

Project Duration: 6 months

 

           

 

 

 

  1. Supply & installation of 400 & 630 Amp Breakers for firefighting system main control panels.

 

Client: Jazi EST. – National Guard Health affairs

Project Budget: 0.4 Million SR

Project Duration: 4 months

 

                                

 

 

 

  1. Supply & installation of complete BMS for water tank building.

 

Client: M. Waleed A. Al-Ghazzawe EST. – National Guard Health affairs

Project Budget: 0.2 Million SR

Project Duration: 3 months

 

                  

 

  1. Supply & installation of 3500 Kg Elevator.

 

Client: M. Mohammed Osama Alsaman EST. – National Guard Health affairs

Project Budget: 0.6 Million SR

Project Duration: 9 months

 

 

  1. Supply & installation of complete BMS for AHU replacement project in NG Hospital

 

Client: Gulf Group – National Guard Health affairs

Project Budget: 2.6 Million SR

Project Duration: 9 months

     

 

 

  1. Supply & installation of Medical Gas system in NG Hospital

Client: SBG – National Guard Health affairs

Project Budget: 4.2 Million SR

Project Duration: 12 months

 

 

  1. Waterproofing project & Epoxy in AFH Hospital

 

Client: Armed Force Hospital

Project Budget: 1.4 Million SR

Project Duration: 4 months

 

 

  1. Supply and installation of Potable water pumps in Faculty Housing

 

Client: Al Arrab Comp. – King Abdulaziz University

Project Budget: 0.4 Million SR

Project Duration: 6 months

 

 

 

  1. Replacement of Chillers and AHU for Old Oncology Center

 

Client: National Guard Health Affairs

Project Budget: 2.4 Million SR

Project Duration: 9 months

 

 

  1. Replacement of Chillers and AHU for Old for Housing Buildings

 

Client: National Guard Health Affairs

Project Budget: 2.75 Million SR

Project Duration: 12 months

 

 

 

  1. Design, Supply and installation of laundry equipment’s

 

Client: National Guard Health Affairs

Project Budget: 2.23 Million SR

Project Duration: 6 months

 

  1. Construction of New Primary Health Care Building in Bahrah

Client: National Guard Health Affairs

Project Budget: 13.7 Million SR

Project Duration: 12 months